Kitchen Remodel Timeline: What 8 Weeks Actually Looks Like

Southlake Luxury Kitchens can deliver a new kitchen in as little as eight weeks — conditions apply, and this post is mostly about what those conditions are.
Eight weeks is achievable when the layout stays put and every material is selected and ordered before demo. It stretches when it doesn't. Here is where the time actually goes.
Before week one: the part nobody counts
This is the phase that decides whether your project runs eight weeks or sixteen, and it happens before a single tool comes out of the truck.
- Design and scope — 1 to 3 weeks
- Material selection — the wild card. Some homeowners finish in a weekend. Some take four months.
- Cabinet lead time — 3 to 8 weeks depending on the line, longer for full custom
- Permits — see our Southlake permit guide
Cabinets are the long pole. They should be ordered before demo starts, not after. A crew standing in an empty kitchen waiting on a cabinet truck is the most common way a remodel doubles in length.
Week 1 — Demo and discovery
Protection goes down first: floors, doorways, HVAC returns taped off. Then the old kitchen comes out.
Demo week is also discovery week. This is when you find out what is behind the walls — the electrical panel that is full, the vent that was never connected to anything, the plumbing rerouted by a previous owner. Expect one or two surprises. Good crews raise them the day they find them.
Weeks 2–3 — Rough-in
Electrical, plumbing and any framing changes. New circuits for the range and dishwasher, added outlets, can lights, under-cabinet wiring, and any gas line work.
Rough inspection happens at the end of this phase. Walls cannot close until it passes. If your project is going to sit for a few days, this is usually where.
Weeks 3–4 — Drywall, paint, flooring
Drywall goes up, gets taped, floated and textured — that is three days minimum with dry time between coats, and there is no way to rush it. Primer and first coats of paint follow. Flooring goes down before cabinets in most kitchens.
This is the quiet stretch where it looks like nothing is happening. Something is.
Weeks 4–5 — Cabinet install
The week it starts to look like a kitchen. Boxes get set, leveled and scribed to walls that are never perfectly straight. Islands get anchored. Crown and trim go on.
Countertop templating happens after cabinets are set, not before — the fabricator measures the actual installed boxes. Then it is 7 to 14 days back to your slab being cut and installed. That gap is real and it is why week 5 often feels like a pause.
Weeks 6–7 — Counters, backsplash, appliances
Slab goes in. Sink and faucet get plumbed. Backsplash tile goes up, grouts, and gets sealed. Appliances land and get connected. Electrical trim-out: switches, outlets, under-cabinet lighting, pendants.
Week 8 — Punch list
Touch-up paint, cabinet door adjustments, caulk lines, hardware, final clean, final inspection. Walk the kitchen with your contractor and write down everything. A good punch list is long and that is fine — it means somebody looked.
What actually causes delays
In rough order of how often they bite:
- Late material selections. Nothing else on this list is close.
- Cabinet lead times underestimated at the start.
- Change orders mid-project — moving an outlet after drywall means opening the wall again.
- Inspection scheduling — usually days, not weeks, but it is not in anyone's control.
- Backordered appliances, especially panel-ready refrigerators and oversized ranges.
Living through it
Two months without a kitchen is the part people underestimate.
- Set up a temporary kitchen somewhere else in the house before demo: microwave, coffee, toaster oven, a folding table. The garage works.
- Move the refrigerator out of the work zone — you can usually keep using it.
- Expect dust everywhere for the first two weeks no matter how well the space is sealed.
- Ask for the crew's daily schedule. Knowing that Tuesday is a quiet day matters if you work from home.
A design-build team helps here because design, ordering and construction are the same group. There is no gap where the designer hands off to a builder who orders the wrong cabinet line.